Epoch AI, an independent research group that studies AI compute, estimates from satellite imagery that Huawei's AI campus in Horinger, Inner Mongolia, holds about 81,000 H100 equivalents of compute, about 7% of the compute at Colossus 2, an AI data-center campus in Tennessee.

This is Epoch's model estimate, with a 90% interval of 36,000 to 141,000, and it assumes the campus holds no export-controlled NVIDIA chips. H100 equivalents convert different chips' compute into a number of NVIDIA H100s. The Colossus 2 figure comes from the same Epoch article, written by Ben Cottier, who leads Epoch's data-center project. Epoch concludes that Chinese data centers aren't short of power; the gap lies in chip performance and energy efficiency. By Epoch's estimate, this campus gets about 40% of the compute per unit of power that leading US campuses get. Epoch infers about 286MW of server power across four completed buildings from cooling equipment visible in satellite images. Combining that with its own estimate of Huawei chip sales, it puts about 105,000 Ascend 910C chips in operation (Epoch AI, 2026-11-06). How we checked →
Source and checks
This item ran in the brief of Nov 13, 2026, alongside 16 other items. How we checked it, the quote checks and what was still missing that day are on that issue's How we checked page.
Cite this item
SecondSource (2026). "Epoch AI, an independent research group that studies AI compute, estimates from satellite imagery that Huawei's AI campus in Horinger, Inner Mongolia, holds about 81,000 H100 equivalents of compute, about 7% of the compute at Colossus 2, an AI data-center campus in Tennessee.." https://secondsource.io/en/news/2026-11-13-7/. Accessed access date.